Cross of Hope Building Project

Thursday, October 27, 2011

10/27/11 New Curb for Parking Lot




Posted by Cross of Hope at 8:46 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Wednesday, October 26, 2011

10/26/11 COH Construction Team

Posted by Cross of Hope at 8:39 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

10/26/11 Extending Septic System








Posted by Cross of Hope at 12:29 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Monday, October 24, 2011

10/24/11 Fire Suppression Tanks




Posted by Cross of Hope at 12:38 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

10/24/11 Building Walls


Posted by Cross of Hope at 12:35 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Wednesday, October 19, 2011

10/19/11 Move Dirt by Steps




Posted by Cross of Hope at 8:58 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

10/19/2011 Install Fire Suppression Tanks





Posted by Cross of Hope at 8:21 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Monday, October 17, 2011

10/17/11 Moving Dirt for Parking Lot




Posted by Cross of Hope at 7:23 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Friday, October 14, 2011

10/14/11 Concrete Floors Completed





Posted by Cross of Hope at 10:09 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

10/14/11 Install Culverts for New Parking Lot






Posted by Cross of Hope at 10:01 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Monday, October 10, 2011

10/10/11 Prepare Narthex for Concrete



Posted by Cross of Hope at 9:31 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

10/10/11 Concrete Floor Admin




Posted by Cross of Hope at 9:27 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Friday, October 7, 2011

10/07/11 Installing Electrical Line to Light Pole


Posted by Cross of Hope at 4:03 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

10/07/11 Concrete Floor for Restrooms and Admin



Posted by Cross of Hope at 3:57 PM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Wednesday, October 5, 2011

10/05/11 Concrete Floor for Preschool Room


Posted by Cross of Hope at 11:13 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October

Monday, October 3, 2011

10/03/11 Final Dirt Packing over Electrical & Plumbing



Posted by Cross of Hope at 6:14 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: October
Newer Posts Older Posts Home
Subscribe to: Comments (Atom)

Followers

Blog Archive

  • ►  2012 (41)
    • ►  June (6)
    • ►  May (7)
    • ►  April (10)
    • ►  March (5)
    • ►  January (13)
  • ▼  2011 (73)
    • ►  December (14)
    • ►  November (23)
    • ▼  October (17)
      • 10/27/11 New Curb for Parking Lot
      • 10/26/11 COH Construction Team
      • 10/26/11 Extending Septic System
      • 10/24/11 Fire Suppression Tanks
      • 10/24/11 Building Walls
      • 10/19/11 Move Dirt by Steps
      • 10/19/2011 Install Fire Suppression Tanks
      • 10/17/11 Moving Dirt for Parking Lot
      • 10/14/11 Concrete Floors Completed
      • 10/14/11 Install Culverts for New Parking Lot
      • 10/10/11 Prepare Narthex for Concrete
      • 10/10/11 Concrete Floor Admin
      • 10/07/11 Installing Electrical Line to Light Pole
      • 10/07/11 Concrete Floor for Restrooms and Admin
      • 10/05/11 Concrete Floor for Preschool Room
      • 10/03/11 Final Dirt Packing over Electrical & Plum...